TVA
Watts Bar Units 1 and 2 –
While employed by Ebasco Engineering, Mechanical Engineering Manager for a
staff 165 engineers and designers engaged in the completion of the design of
the TVA Watts Bar Unit 1. Responsible for staff planning and budget
management of approximately $20M/year. Also responsible for the
preliminary staffing for the engineering completion of TVA Watts Bar Unit
2. Responsible for the technical quality of the engineering work and
conformance with client and corporate engineering procedures and industrial
codes and standards
WPPSS
Units 1-5 –
While employed at the Washington Public Power Supply System Corporate
Headquarters, managed the Design Assessment Department. Responsible for the
interdisciplinary review of engineered systems. Prepared annual work,
budget, and schedule reports and forecasts for the department.
Responsible for department staffing. Conducted personnel performance
reviews and interviews and hiring of new engineering and clerical staff.
Provided technical direction to a staff of senior level engineers engaged in
the design review of nuclear safety systems. While employed at the WNP-3
Project, managed the developed of the Engineering Baseline that included a
description of the work scope, schedule, and budget for the completion of over
1,000 engineering tasks. Established a Project Engineering
interdisciplinary design review program for the technical and operational
review of power plant systems. Provided technical direction to a staff of
engineers engaged in the technical review of the project Architect-Engineer's
design. Established design criteria and monitored the A/E engineering
performance. Prepared the engineering and design of the fire protection
system both as a member of the WPPSS engineering staff and later as a member of
the Ebasco engineering staff. This included preparation of fire zone maps
and NRC Appendix R, FSAR and contractor specification and drawing reviews.
PG&E Diablo Canyon Unit 1 and 2 – While employed by Pacific Gas & Electric Company, responsible for system design and approval of mechanical drawings for the balance of plant (BOP) systems for the Diablo Canyon Power Plant. Provided mechanical engineering coordination for other discipline drawings. Provided assistance to other projects requiring fluid analysis and computer programming. Provided technical assistance to the B31.1 Subcommittee in writing the "Non-Mandatory Appendix for Safety Relief Valve Installations." Participated in the engineering and design of the fire protection system. Assisted in the preparation of the fire protection section of the FSAR. Provided technical interface with the NRC and project insurers.